The weekend did not play out exactly as planned, however the amount progress was the same if not greater than expected.
A few updates:
· drywall is now hung on the east side but did not begin on the west
· ALL of the ceiling track is now installed
· framing in the kitchen is complete
· HVAC will continue this week
· framing for west offices to begin tomorrow
· drywall taping and sanding to continue this week
· kitchen layout was finalized today and finishes were selected
· plumbing rough to begin this week
Stay tuned for more pictures...