Monday, January 25, 2010

Drywall, Paint, Lighting and Photos...what more do you want?

Saturday was another busy day at 222, see update below...

Drywall for the offices on the West side of the space is well underway.  Taping and sanding on the east side will be complete by Wednesday and will begin taping and sanding the west side on Thursday.  HVAC is 70% finished and will be complete by the end of the week.  Painting will begin this week! Sprinkler pipes have already been painted.   I selected wall colors last week and will test and approve each color on Tuesday.   I now have 90% of the decorative light fixtures on site and have a few options for the entry. Those will be hung and a decision made by the end of the week.  They are all very cool fixtures…this is will be a tough decision!  New pictures added today also.